It's often during critical situations that the true skills and experience of our people is revealed. This was the case when a High Voltage Direct Current (HVDC) conductor (wire) fell across State Highway 7 in the Weka Pass area, Waikari in North Canterbury, New Zealand.
What started out as a standard day quickly escalated when the southern lines team, part of our broader Electricity & Gas team, received the call at 3.08pm regarding the fault which caused the line to fall.
Partnering with our client, the team jumped to action, dispatching a helicopter to the location. Field teams were also mobilised and sent to site to clear the road and open the Highway. The Highway was reopened that evening but the critical work of restoring the line, and power continued.
The crew works safely at height on repairing the critical equipment.
Responding to a range of challenges
To complicate matters further, New Zealand went into a level 4 COVID-19 lockdown on the same day and the area was experiencing a range of poor weather conditions including temperatures as low as -4°C to 20°C, strong winds (up to 80kph some days) and rain.
Ventia Operations Manager Mike O'Brien assessed the damages.
Arriving at the location the team in the helicopter reported that the damage was worse than expected with a number of additional issues.
Collaboration between response teams
Our client Transpower set up a national response team to manage the repair process that included Ventia people, and the team met daily. Ventia also set up an on-the-ground southern response team, located at the Islington office which was supported by the local Transpower service delivery manager and engineer.
At the peak of the operation, we had approximately 40 staff on site including sub-contractors. The team utilised all equipment at their disposal including cranes, crane trucks, diggers, a bulldozer, tractor winches and helicopters. Most of the responding team were accommodated in (Amberley), 40-minutes north of Islington and the work site was an hour north of Islington meaning travel was required to and from site on a daily basis. Extra support staff were also mobilised from Washdyke, Wellington, Rotorua, Napier, and Hamilton.
Helicopter view of a tower where the conductor cable had broken off at attachment.