Storm damage to the high-voltage network and widespread power outages in the region surrounding Woomera, South Australia
Critical systems kept operational throughout the outage with emergency back-up generators and robust food and fuel stocks.
Power was returned and the team carefully managed the end of the outage avoiding surges and equipment damage
While ElectraNet, the local energy provider, worked to restore power, Ventia ensured continuity for Defence and the Woomera community.
The Ventia team was well prepared with emergency back-up generators and robust food and fuel stocks. We initially worked with Defence to determine how to respond to the outage. With additional hired generators, we kept critical systems operational throughout the outage. A trailer-mounted back-up generator, and additional generators provided free-of charge by BHP at Olympic Dam, provided additional assurance.
Power was restored yesterday which is great. Ventia have been keeping us well updated and the team have done a fantastic job - Jason Armstrong
Ventia successfully kept critical infrastructure humming including:
We cleared roadways of fallen trees, and worked across the whole base to make safe, complete critical maintenance, and remove debris. The Ventia fire team conducted continuous patrols of buildings which lacked power for fire alarms.
Power was returned on 3rd November, and the team carefully managed the end of the outage. We chose to stagger residents returning to their homes to avoid an overload on air-conditioning units. Electricians also switched off mains power in unused accommodation to avoid surges and equipment left inadvertently on.